  • Warriewood monthly update - July 2017

    4 days ago
    Img 7126

    In Warriewood, construction work will continue in the car park and on Pittwater road. Works will include construction of the car park foundation and pavement at the entry to the rugby park.

    Most work will be carried out during the day, however some night work will be required for the
    safety of workers, pedestrians and road users and to minimise traffic impacts.

    For more information visit our Warriewood monthly update July 2017

    In Warriewood, construction work will continue in the car park and on Pittwater road. Works will include construction of the car park foundation and pavement at the entry to the rugby park.

    Most work will be carried out during the day, however some night work will be required for the
    safety of workers, pedestrians and road users and to minimise traffic impacts.

    For more information visit our Warriewood monthly update July 2017
  • Warriewood - June update 2017

    19 days ago
    Img 7127

    Upcoming day work at Warriewood will include pavement construction during early June in the temporary car park area and piling work in mid-June. Works will take approximately 4 weeks to complete, weather permitting. The standard working hours for work at Warriewoodwill be 7am to 6pm Monday to Friday and 8am to 1pm on Saturday.

    For further information please visit Warriewood June 2017 update

    Upcoming day work at Warriewood will include pavement construction during early June in the temporary car park area and piling work in mid-June. Works will take approximately 4 weeks to complete, weather permitting. The standard working hours for work at Warriewood will be 7am to 6pm Monday to Friday and 8am to 1pm on Saturday.

    For further information please visit Warriewood June 2017 update

  • The new Northern Beaches Booklet

    19 days ago
    Capture

    We invite you to download the new Northern Beaches Booklet now available at the Northern Beaches Bus Service Plan link

    We invite you to download the new Northern Beaches Booklet now available at the Northern Beaches Bus Service Plan link

  • Mona Vale - Upcoming Night work - June 2017

    24 days ago
    Img 7111
    We will be carrying out median modification work along Barrenjoey Road and underground service relocation at the corner of Park Street. The work is scheduled to take place between 7pm and 6am on Wednesday 7 June and Thursday 8 June 2017, weather permitting.

    For more information see Mona Vale Night work update

    We will be carrying out median modification work along Barrenjoey Road and underground service relocation at the corner of Park Street. The work is scheduled to take place between 7pm and 6am on Wednesday 7 June and Thursday 8 June 2017, weather permitting.

    For more information see Mona Vale Night work update

  • B-Line extension to Newport announced

    27 days ago
    B line 3

    Transport Minister Andrew Constance today announced the extension of the Northern Beaches B-Line route to Newport, along with a number of changes to the local bus network new routes, improvements to existing routes and more peak hour services.

    "We’ve made the decision to extend the B-Line route from Mona Vale to Newport which will make it even easier for customers from Newport and the surrounding areas to travel to-and-from the Sydney CBD."

    Changes to the Northern Beaches Bus Network will come into effect later this year to coincide with the launch of the B-Line and can be viewed online at the Northern Beaches Bus Service Plan page. New timetables will be available closer to changeover.

    Transport Minister Andrew Constance today announced the extension of the Northern Beaches B-Line route to Newport, along with a number of changes to the local bus network new routes, improvements to existing routes and more peak hour services.

    "We’ve made the decision to extend the B-Line route from Mona Vale to Newport which will make it even easier for customers from Newport and the surrounding areas to travel to-and-from the Sydney CBD."

    Changes to the Northern Beaches Bus Network will come into effect later this year to coincide with the launch of the B-Line and can be viewed online at the Northern Beaches Bus Service Plan page. New timetables will be available closer to changeover.

  • Upcoming night work - Mona Vale

    about 1 month ago
    Img 7034
    We will be relocating underground services at the corner of Park Street and Barrenjoey Road outside of normal work hours.

    The work is scheduled to take place between 7pm and 6am on Monday 29 May 2017 and Tuesday 30 May 2017, weather permitting. Our work will include: minor earthwork including excavating trenches, installing and relocating services and cables and removing sections of the existing kerb and minor concreting.

    For more information see Mona Vale night work update

    We will be relocating underground services at the corner of Park Street and Barrenjoey Road outside of normal work hours.

    The work is scheduled to take place between 7pm and 6am on Monday 29 May 2017 and Tuesday 30 May 2017, weather permitting. Our work will include: minor earthwork including excavating trenches, installing and relocating services and cables and removing sections of the existing kerb and minor concreting.

    For more information see Mona Vale night work update

  • Mona Vale update - May

    about 1 month ago
    Mv impression

    Upcoming day work at Mona Vale will include concrete cutting to locate services and investigation works in the median including soil sampling and pavement coring.

    The standard working hours for work at Mona Vale will be 7am to 6pm Monday to Friday and 8am to 1pm on Saturday.

    The footpath along Barrenjoey Road between Pittwater Road and Park Street will be closed during construction. Alternate routes through Village Park are available.

    More information about upcoming work is available in the May Mona Vale update.


    Upcoming day work at Mona Vale will include concrete cutting to locate services and investigation works in the median including soil sampling and pavement coring.

    The standard working hours for work at Mona Vale will be 7am to 6pm Monday to Friday and 8am to 1pm on Saturday.

    The footpath along Barrenjoey Road between Pittwater Road and Park Street will be closed during construction. Alternate routes through Village Park are available.

    More information about upcoming work is available in the May Mona Vale update.


  • Spit Bridge to Neutral Bay B-Line proposal approved

    about 1 month ago
    Spit junction image

    TfNSW has received planning approval for the B-Line program between Spit Bridge and Neutral Bay, which features a series of road improvement work to improve bus travel time and reliability between the Northern Beaches and the Sydney CBD.

    A total of 342 submissions were received throughout the public display of the proposal in December 2016 and January 2017.

    Key matters raised included concerns about parking, congestion, the relocation of bus stops, turning restrictions, environmental concerns and construction questions.

    The approved proposal includes the removal of the following items from the scope of works:

    TfNSW has received planning approval for the B-Line program between Spit Bridge and Neutral Bay, which features a series of road improvement work to improve bus travel time and reliability between the Northern Beaches and the Sydney CBD.

    A total of 342 submissions were received throughout the public display of the proposal in December 2016 and January 2017.

    Key matters raised included concerns about parking, congestion, the relocation of bus stops, turning restrictions, environmental concerns and construction questions.

    The approved proposal includes the removal of the following items from the scope of works:

    • the construction of a new left hand turn lane from Spit Road (city bound) into Awaba Street, Mosman
    • the permanent relocation of the M30 bus layover from Spit Road to Military Road east
    • the construction of an indented bus bay on Military Road (citybound) between Murdoch Street and Hampden Avenue
    • all proposed turn restrictions at the intersection of Military Road/Ben Boyd Road
    • the proposed section of tidal flow at Ben Boyd Road,Neutral Bay.


    The following scope item has been revised following community feedback:

    • the distance of relocation of outbound and citybound local bus stops from their existing location at Cremorne has been reduced.

    A Submissions Report has been produced to provide further details about the proposal and responses to feedback.
  • Upcoming work at Narrabeen

    about 1 month ago
    Narrabeen

    Upcoming day work at Narrabeen will include relocating and modifying the existing footpath and some vegetation removal. We will also demolish the existing amenities block which will involve concrete cutting, a small excavator and removing the materials.

    A temporary amenities facility has been provided for the duration of the project.

    The work will be carried out during the day from 7am to 6pm Monday to Friday and 8am to 1pm Saturday.

    Conditions within the car park have changed. Please obey the signage in place.

    More information about upcoming work is available in the May Narrabeen update.


    Upcoming day work at Narrabeen will include relocating and modifying the existing footpath and some vegetation removal. We will also demolish the existing amenities block which will involve concrete cutting, a small excavator and removing the materials.

    A temporary amenities facility has been provided for the duration of the project.

    The work will be carried out during the day from 7am to 6pm Monday to Friday and 8am to 1pm Saturday.

    Conditions within the car park have changed. Please obey the signage in place.

    More information about upcoming work is available in the May Narrabeen update.


  • Latest update on work at Warriewood

    about 2 months ago
    Wwood
    Night work at Warriewood will take place on Pittwater Road (adjacent to the car park) on Wednesday 10 May 2017 and Thursday 11 May 2017, weather permitting. The work will involve concrete cutting and service location around the median.

    The work will be carried out from 7pm to 5am.

    Upcoming day work at Warriewood includes the start of piling, which will begin at the northern end of the car park and take around three weeks to complete.

    Car park changes

    The commuter car park entrance is currently restricted to one lane during construction hours on weekdays and... Continue reading
    Night work at Warriewood will take place on Pittwater Road (adjacent to the car park) on Wednesday 10 May 2017 and Thursday 11 May 2017, weather permitting. The work will involve concrete cutting and service location around the median.

    The work will be carried out from 7pm to 5am.

    Upcoming day work at Warriewood includes the start of piling, which will begin at the northern end of the car park and take around three weeks to complete.

    Car park changes

    The commuter car park entrance is currently restricted to one lane during construction hours on weekdays and is entry only. A detour is available for vehicles exiting the car park.

    In order to construct the new car park, around 50 spaces will be unavailable from May 2017 until the car
    park is opened later this year.

    More information about upcoming work is available in the May Warriewood update.