Mosman and Spit Junction

In August, property boundary adjustments and utility relocation works continued for the construction of the new bus indent on Military Road at Prince Street, whilst utility relocation work continued in Mosman for the extension of the bus indent on Spit Road at Parriwi Road.

Throughout September, the majority of these works will continue at Prince Street and Parriwi Road, whilst site inspections will be undertaken to assess remaining works for project completion late 2019.

The following activities will continue for bus indents along Spit and Military Roads throughout September:

Bus indent at Parriwi Road

Day work will be required to complete the work program and will be undertaken from 7am to 6pm Monday to Friday and 8am to 1pm Saturday. Work will include:

  • watermain relocation
  • other utilities adjustments
  • civil works to extend the bus indent

Bus indent at Prince Street

Day work will be required to complete the work program and will be undertaken from 7am to 6pm Monday to Friday and 8am to 1pm Saturday. Work will include:

  • watermain relocation
  • other utilities relocations and Telstra cabling
  • civil works and construction of new drainage and pavements

Additional activities in Mosman

  • replacement of a temporary tidal flow sign with an electronic sign on Spit Road, between Awaba Street and Killarney Street
  • site walks to assess remaining activities required as part of finishing works

For more information regarding works in Mosman and Spit Junction, please see the latest notification here

The scope of works delivered in Mosman include:
  • new B-Line and local stops northbound and southbound
  • new bus indent at Clifford Street Road widening between Clifford Street and Civic Lane
  • new additional canopy for bus customers at the citybound B-Line bus stop


In August, property boundary adjustments and utility relocation works continued for the construction of the new bus indent on Military Road at Prince Street, whilst utility relocation work continued in Mosman for the extension of the bus indent on Spit Road at Parriwi Road.

Throughout September, the majority of these works will continue at Prince Street and Parriwi Road, whilst site inspections will be undertaken to assess remaining works for project completion late 2019.

The following activities will continue for bus indents along Spit and Military Roads throughout September:

Bus indent at Parriwi Road

Day work will be required to complete the work program and will be undertaken from 7am to 6pm Monday to Friday and 8am to 1pm Saturday. Work will include:

  • watermain relocation
  • other utilities adjustments
  • civil works to extend the bus indent

Bus indent at Prince Street

Day work will be required to complete the work program and will be undertaken from 7am to 6pm Monday to Friday and 8am to 1pm Saturday. Work will include:

  • watermain relocation
  • other utilities relocations and Telstra cabling
  • civil works and construction of new drainage and pavements

Additional activities in Mosman

  • replacement of a temporary tidal flow sign with an electronic sign on Spit Road, between Awaba Street and Killarney Street
  • site walks to assess remaining activities required as part of finishing works

For more information regarding works in Mosman and Spit Junction, please see the latest notification here

The scope of works delivered in Mosman include:
  • new B-Line and local stops northbound and southbound
  • new bus indent at Clifford Street Road widening between Clifford Street and Civic Lane
  • new additional canopy for bus customers at the citybound B-Line bus stop